Milestone slip: how to measure and report milestone delays

Milestone slip is the number of days between a milestone's baseline date and its current forecast. A milestone planned for 1 December and now forecast for 19 December has slipped 18 days.

Where the baseline comes from

How the Project Health Check shows it

What to do when a milestone slips