Free milestone plan template for Excel (baseline vs forecast)

A free milestone plan template for Excel to track your milestones against the agreed dates. Enter the baseline once, update the forecast at each status meeting, and the slip in days is calculated for you.

Download the template (.xlsx)

What's inside

ColumnUse
Task IDUnique code (M1, M2, …); never change it
TitleMilestone name
OwnerWho is responsible
PhaseIntake, Preparation, Execution, Handover, Close
Baseline dateThe originally agreed date; set once
Forecast dateCurrent best estimate; update regularly
Completed dateDate the milestone was reached
StatusNot started, In progress, Completed
Type"Milestone"
Slip (days)Calculated: forecast − baseline
NotesReason for changes

See it as a timeline

Load the file into the Project Health Check. Because it has a baseline column, one file is enough: you get a milestone timeline with baseline vs forecast, a slip table and next steps for each delayed milestone.

Need tasks as well?

Use the project plan template with phases, tasks and milestones.